MassDOT will seek bids on Green Line engineering work
The Massachusetts Department of Transportation (MassDOT) will put out to bid the preliminary engineering work for the Green Line Extension project, after failing to get MassDOT board of directors support Tuesday for a contract amendment that would have covered the cost of the work.
David Mohler, Executive Director of Planning for MassDOT, withdrew a proposal to the board for a $24.5 million contract extension with a consulting group led by Vanasse, Hangen, Brustlin (VHB), after board members expressed concerns about the process.
VHB has been the lead consultant on the Green Line Extension environmental impact studies over the last three years, and its original $2.8 million contract for that work had previously been amended four times at a total additional cost of $9 million. But another amendment, although permissible according to the original contract, did not sit well with the board.
“I’m bothered by a contract that went from $2 million to $12 million and now would go to $36 million without another solicitation process,” board chair John R. Jenkins told Mohler. “It doesn’t feel good and I’m not assured we’re getting our value out of this project.”
Board member Janice Loux agreed, saying, “I think we are better served as an agency if we rebid this contract and with a closer eye on the subcontractors.”
MassDOT had presented the proposed amendment to the board at its August meeting, which was cut short when board member Elizabeth Levin recused herself from the vote, leaving the body short of a four-person quorum. Before that occurred, board members had questioned MassDOT presenter Steve Woelfel about the unusual nature of the procurement process, and also asked for more information about the qualifications of the proposed project team for preliminary engineering.
For Tuesday’s meeting, the board was provided memos addressing the propriety of the contract amendment, an overview of the proposed project team’s experience, and a six-page list showing the Green Line Extension “Civic Engagement Log” of public meetings and other events since October 2007 when the original VHB contract took effect. But the board remain unconvinced.
“I’m personally committed to this project and the last thing I want to do is slow it down, but I don’t think you’ve provided any new information since last month’s meeting,” said board member Andrew Whittle. “We’ve lost another month.”
The effect of Tuesday’s board inaction on the Green Line Extension project’s overall timetable was unclear. MassDOT officials had told the board that having to put the preliminary engineering contract out to bid could delay the project from 3 to 12 months. Jenkins questioned that estimate, and urged MassDOT to try to complete the procurement process in 60 days.
Mohler also noted that Transportation Secretary Jeffrey Mullan has discretion to authorize expenditures of up to $5 million for the project without board approval, meaning the existing VHB contract could again be amended in order to keep the project moving forward while bids are sought for preliminary engineering.
MassDOT has scheduled public information meetings on the Green Line Extension project for Sept. 28 in Somerville and Sept. 29 in Medford. Those sessions are to include an overview of the project work to date, and new information on the requirements the MBTA uses to design its stations. Public workshops on the Community Path extension in Somerville and on individual Green Line stations, along with a second meeting of the project Design Working Group, are being planned for October through December.
In July, MassDOT announced a delay in its projected completion schedule of Phase I of the Green Line Extension – to College Avenue in Medford and Union Square in Somerville – from Dec. 31, 2014 to October 2015.